Present Status

Physical Progress
Infrastructure Development 100%
Civil Works 96%
Hydro Mechanical Works 96%
Transmission Line 80%
Documentation Progress

Project Development:

  • Survey licenses obtained for 7.3 MW, with additional 2.3 MW capacity.
  • Hydrological investigation verifies dry energy potential.
  • Geological investigation and research enhance design and protection measures.

Project Documentation:

  • Detailed Project Report (DPR) completed by Units Engineering Consultancy Pvt. Ltd.
  • Connection agreements finalized for 7.3 MW, with 2.3 MW under process.
  • Power Purchase Agreement (PPA) completed for 9.6MW
  • Initial Environmental Examination (IEE) approved for 9.6 MW
  • Generation license No.BBB 073/74 BU 183 obtained for 9.6MW is valid upto 2108/10/22 

Financial Aspects:

  • Due diligence Audit (DDA) report deems project feasible and attractive for investors.
  • Financial closure with Nepal Infrastructure Bank Limited(Lead) & NIC Asia Bank Limited(Member) 

Infrastructure and Connectivity:

  • Access road construction connects project to Madhya Pahadi Highway.
  • Camp for Project Completed
  • Construction Power Available
  • Communication system available

Power Purchase Agreement (PPA):

  • PPA signed with Nepal Electricity Authority (NEA) defining rates and Commercial Operation Date (RCOD) is for 7.3 MW capacity 2079/10/21 and for 2.3 MW 2080/3/12 and further extension process is ongoing.