Present Status
Physical Progress
Infrastructure Development
100%
Civil Works
96%
Hydro Mechanical Works
96%
Transmission Line
80%
Documentation Progress
Project Development:
- Survey licenses obtained for 7.3 MW, with additional 2.3 MW capacity.
- Hydrological investigation verifies dry energy potential.
- Geological investigation and research enhance design and protection measures.
Project Documentation:
- Detailed Project Report (DPR) completed by Units Engineering Consultancy Pvt. Ltd.
- Connection agreements finalized for 7.3 MW, with 2.3 MW under process.
- Power Purchase Agreement (PPA) completed for 9.6MW
- Initial Environmental Examination (IEE) approved for 9.6 MW
- Generation license No.BBB 073/74 BU 183 obtained for 9.6MW is valid upto 2108/10/22
Financial Aspects:
- Due diligence Audit (DDA) report deems project feasible and attractive for investors.
- Financial closure with Nepal Infrastructure Bank Limited(Lead) & NIC Asia Bank Limited(Member)
Infrastructure and Connectivity:
- Access road construction connects project to Madhya Pahadi Highway.
- Camp for Project Completed
- Construction Power Available
- Communication system available
Power Purchase Agreement (PPA):
- PPA signed with Nepal Electricity Authority (NEA) defining rates and Commercial Operation Date (RCOD) is for 7.3 MW capacity 2079/10/21 and for 2.3 MW 2080/3/12 and further extension process is ongoing.